A Construction Project Organization Design for Cable Laying Work in an Expansion

This document, titled "Project Organization Design for Cable Installation Work of an Expansion Project," is a comprehensive plan outlining the execution strategy for a specific phase of a building or infrastructure expansion project that involves cable laying. It is a crucial plan that details the procedures, schedules, resources, and methods for the installation of electrical cables, which are vital for the functionality and efficiency of the upgraded facility.

The design may cover topics such as:

1. Project Overview: A brief introduction to the project, including its objectives, location, and the specific cable types to be installed. 2. Scope: Definition of the cable laying tasks, including the routes, lengths, and the types of cables that need to be laid. 3. Site Preparation: Procedures for clearing the site, marking cable paths, and preparing the ground for cable installation. 4. Equipment and Materials: List of required tools, machinery, and materials, including specifications and suppliers. 5. Work Schedule: A detailed timeline for different stages of the cable laying process, including planning, installation, testing, and commissioning. 6. Safety and Health Measures: Implementation of safety protocols to ensure the well-being of workers and prevent accidents. 7. Quality Control: Procedures and standards for inspecting and testing the cables and the overall installation to ensure quality and compliance with regulations. 8. Emergency Procedures: Plans for handling any unforeseen situations or emergencies during the cable laying process.

Overall, this document serves as a blueprint for coordinating the efficient and effective execution of the cable laying work, ensuring the project's success and meeting the project's goals.

某扩建项目电缆敷设工程施工组织设计(英汉)部分内容预览:

3) post responsibility. Project manager take charge of the project quality,subdivision responsibility, right clear. According to the differences of everyone to confirm different position, make every position have person, every person have position.

5.3.3.2机具保证

5.3.3.2 machines and tools guarantee

机具选型。针对施工工艺要求、现场情况等,按照技术上先进、经济上合理、生产上适用、性能上可靠、使用上安全、操作*便和维修*便的原则铝合金门窗安装施工工艺,结合公司机械设备情况和租赁或**能力,合理选择机械设备。

1) choose the type of machines and tools. Aim at requirement of process, arena condition, according to the rules that advanced technique, reasonable economic, applicable in production, trusty capability, safe use, conveniency operating and maintain, choose appropriate mechanical equipments.

机具检查。对所有施工设备进行检查与保养,损坏的尽快修理,修理不好的机具及缺少的机具采取租赁或**的**,保证工程施工能够顺利进行。

2) inspection. Inspect and maintain every equipments, repair the damaged as soon as possible to make sure the project go with a swing.

机具操作。每一种机具都必须由熟练的操作工人来使用,对新租赁或*进的机具,详细阅读使用说明书,指定专人学习,尽快掌握操作要领。

3)Operation. Every machines and tools must be operated by skilled worker, for new one, read the use introduce, designate person to study, and master the main point as soon as possible.

5.3.3.3设备、材料保证

5.3.3.3 equipments and materials guarantee

设备、材料选择。设备、材料质量的好坏直接关系整个工程的工程质量,所以设备、材料的选择必须以优质为前提,在符合设计及相关要求的基础上,选择价低的产品。

1) equipments and materials’ choice. equipments and materials’ quality impact the project quality directly, so the choice of equipments and materials must be quality, on the basis of according with design and relevant requirements, choose low price production.

设备、材料运输。设备、材料的运输要符合产品本身的要求,对有特殊要求的设备、材料单独运输或采取有效措施,保证设备、材料合格到达施工现场。

2) equipments and materials’transport. equipments and materials’transport should accord with the requirement of equipments and materials, for equipments and materials which have special requirements , transport alone so that ensure equipments and materials arrive at arena.

设备、材料验收。对到达施工现场的设备进行严格的质量验收。由质检人员对设备、材料的外观、零部件及功能等主要*面进行验收,不合格的产品不与接受,以保证不合格的产品不会流入到施工环节。

3) equipments and materials’ checking and accepting. Check and accept the equipments and materials strictly, the unqualified productions will not be accepted to make sure that unqualified productions can not get in construction link.

设备、材料保管。根据设备、材料的具体性质对其进行分类保管,并有专人看管。

4)equipments and materials’safekeeping. According equipments and materials’specification character to keeping claaify and take charge by assigned person

不合格品处理。对于不合格品,要与合格品分开,做明显标识。能够检修合格的材料,在不影响施工安排的情况下立即返厂,否则,另*新品以保证施工顺利进行。如果是用户提供的材料,将情况如实反映给用户,本着友好的态度协商解决.

5) reject’s disposal. For reject, divide with quality products, make evident mark. The materials which can examine and repair, if don not impact schedule, retune factory immediately, otherwise, buy new products.

设备、材料使用。根据设备、材料特性合理使用,保证安装质量。

6) equipments and materials’use. According to equipments and materials’reasonable use, insure quality.

5.3.3.4施工*法保证

5.3.3.4 construction method guarantee

技术交底。坚持两级技术交底制度,即施工前由公司对项目经理部及项目经理部对全体施工人员进行技术交底工作,使施工人员做到心中有数.

三级检查。坚持质量的“三级检查制度”,即自检不合格不移交,互检不合格不接受,未经质检人员检查验收签字,不准进入下道工序施工。

2)third class inspection. Insist on third class inspection system, namely, disqualification do not hand over inspect by self, disqualification do not hand over inspect by each other, forbid to get in the next procedure if the inspector do not sign.

“三工序”活动。开展“三工序”活动,即复查上道工序的质量,保证本道工序的质量,准时、优质的为下道工序服务。

3) three working procedures. Countercheck prior working procedure’s quality, ensure this working procedure’s quality, high quality service for the next working prodecure.

不合格项处理。对施工中产生的不合格项要立即制止并强制整改,直到检查合格后*可进行下一步工序,不合格项要做详细的记录,并做认真分析其发生的原因,制定纠正预防措施,杜绝此类情况在下一工程中发生。

4)deal with disqualification item. Refrain and stop the disqualification item in the process of construction, can not do the next procedure until measure up, the disqualification item must record and analyse the reason, establish correcting and preventing measure.

成品保护。对已完成的工序要做好保护措施DB23∕T 3368-2022 沥青路面冷再生设计与施工技术规程,防止重复施工情况发生。

5.3.3.5施工环境保证

5.3.3.5 construction environment guarantee

天气情况。对天气情况充分了解某工程冬季施工*案2,根据天气情况,合理安排或调整施工工序,保证施工顺利进行。

1) weather condition. Kown weather condition, according to the weather condition, arrange and adjust working procedure, ensure the construction going on.

现场情况。与土建部门密切沟通,实时了解土建工程进展情况,合理安排各设备的安装顺序。如有必要,与土建部门充分协商,改变土建内部装修顺序,例如GIS组合电器安装周期较长,对安装环境要求较高,可以与土建部门协商,先对组合电器室的内部进行装修处理。