资源下载简介
高模施工方案简介:
高模施工方案部分内容预览:
=0.02mm<600/400=1.25mm 满足要求
V=1.286×3.75=4.82KN
τ=3V/2bh=3×4820÷(2×489×2)
房建工程施工组织设计范本=7.39N/mm2<[τ]=110 N/mm2 满足要求
5.8 对拉螺栓验算
N=25×0.6×0.48=7.2KN
用M12对拉螺栓 [N]=12.9KN>N=7.2KN 满足要求
5.9 支撑架立杆验算
(1) 梁底横大楞传来重 (10.45×0.6)÷2=3.135KN
(2)大楞自重: 0.037KN/m×1.2=0.03KN
(3)立杆自重: 0.037×11×1.2=0.49KN
(4)扣 件重: 14个×0.018KN/个=0.25KN
(5)水平横杆重:0.037KN/m×7×(0.6+0.9)=0.39KN
N=4.3KN
M=Ne=4.3×0.048=0.21KN·m
用步距为1.5m时 A=489mm2
λ=l0/i=1500/15.78=95.06 φ=0.626
=N/φA +M/W =4300÷(0.626×489)+210000/5080
=55.39N/mm2<[]=215N/mm2 满足要求
5.9.2、抗滑移验算
N=10.43KN>8KN 底模大楞与立杆连接处用2个扣件可满足要求。
支撑架立杆支承于地下室顶板上,利用支架下座即可承担上部传来荷载,故不需作基础处理,即能满足安全要求。
6.1 模板验算(按板厚180mm考虑)
荷载:砼板自重: 25KN/m3×0.18=4.5KN/m2
钢筋重: 1.5×0.18=0.27KN/m2
18厚胶合板自重:6.0×0.02=0.12KN/m2
g=1.2g1=4.89×1.2=5.868KN/ m2
施工荷重:P=2.5×1.4=3.5 KN/m2
强度验算:(按四跨连续板验算)
Mmax=(0.107×5.868+0.121×3.5)×0.42=0.168KN·m
W=bh2/6=1000×18×18/6=54000mm3
=M/W=168000/54000=3.11 N/mm2<[]=16N/mm2 满足要求
V=(0.607×5.868+0.62×3.5) ×0.4=2.293KN
τ=3V/2bh=3×2293÷(2×1000×18)
=0.191 N/mm2<[τ]=2.2 N/mm2 满足要求
W=(0.632×5.868+0.967×3.5)×4004÷(1×100×104×1000×183/12)
=0.374mm<400/400=1.0mm 满足要求
6.2 小枋木验算(按单跨梁计小楞间跨400mm)
g=5.868×0.4=2.35KN/m
P=3.5×0.4=1.4 KN/m
Mmax=0.125×375×12=0.47KN·m
W=50×1002/6=83333mm3
=M/W=470000/83333=5.6 N/mm2<[]=13N/mm2 满足要求
V=3.75×1/2=1.88KN
τ=3V/2bh=3×1880÷(2×100×50)
=0.564 N/mm2<[τ]=1.4 N/mm2 满足要求
W=5q·l4/384EI=5×3.75×10004÷(384×1.0×104×50×1003/12)
=1.172mm<1000/400=2.5mm 满足要求
6.3 大楞验算 (Ф48×3.5钢管)
(为简化计算按均布荷载考虑计)
g=5.868+0.03×3+0.037=6.0KN/m
P=3.5KN/m (荷载组合:q=6+3.5=9.5KN/m)
强度验算(按三跨连续梁计)
Mmax=(0.117×9.5×0.9)=1.0KN·m
=M/W=1000000/5080=196.85N/mm2<[]=215N/mm2 满足要求
V=0.617×9.5×0.9=5.28KN
τ=5280/489=10.8 N/mm2<[τ]=110 N/mm2 满足要求
W=KWql4/100EI=0.99×9.5×10004÷(100×2.1×106×12.18×104) =0.368mm<1000/400=2.5mm 满足要求
6.4 支撑架立杆验算
大楞传来荷重:5.28KN
立杆自重: 11×0.037=0.4KN
扣 件 重: 8×2×0.018KN/个=0.3KN
水平拉杆重: 8×2×0.037=0.6KN
M=6.58×0.048=0.316KN·m
用Ф48×3.5钢管,间距0.9×0.9m,步距1.5m
I=15.78mm λ=l0/i=1500/15.78=95.06 φ=0.626
σ=6580÷(0.626×489)+ 316000/5080
=83.7N/mm2< 215N/mm2 满足要求
抗滑移验算:N=6.93KN<8KN 用一个扣件即可。
7、Z43柱模板验算:700×700mm截面尺寸
柱高6m分两次支模浇完,砼浇筑速度
V=1.80m/h β1=1.2 β2=1.15 T=300C t0=200/30 +15=4.45
F= 0.22Rc·t。·β1·β2·V1/2 = 0.22×25×4.45×1.2×1.15×
= 33.78×1.34 = 45.3KN/m
F=Rc.H=25×2.0 = 50KN/㎡
取F=45.3 KN/㎡
模板验算:按两跨连续计算
用50×100松方木,间距300mm
M= 0.125×45.3×0.32 = 0.509KN.m
W=1000×182/6 = 54000mm3
= M/W = 509000/54000 = 9.4 N/mm2 < []=16N/mm2 满足要求
V= 0.625×45.3×0.3 = 8.49 KN
τ= 3V/2bh = 3×8490÷(2×1000×18)= 0.7 N/mm2<[τ]=2.2 N/mm
W=(0.912×45.3×l4)/100EI= 45.6×3004÷(100×1.1×104×1000×18312)= 0.62mm<300/400=0.75 mm满足要求
7.2 竖向立档验算:按跨度500mm四跨验算
q=45.3×0.3=13.6KN/m
Mmax=0.107×13.6×0.452=0.295KN.m
W=50×1002/6=83333mm3
=M/W=295000/83333=3.54 N/mm2<[]=13N/mm2 满足要求
V=0.607×13.6×0.45=3.71 KN
τ=3V/2bh=3×3710÷(2×100×50)=1.11 N/mm2<[τ]=1.4N/mm
W=0.632×13.6×4504÷(100×1.1×104×500×103÷12) =0.08mm<500/400=1.25 mm 满足要求
7.3.1 柱宽700mm向:用2根Ф48×3.5钢管
荷载 P=45.3×0.3×0.45=6.1KN
W=2×5080=10160mm3
=M/W=1710000/10160=168.3 N/mm2<[]=215N/mm2 满足要求
[ν]=489×110=53.7 N/mm2>V=6.1N/mm2 满足要求
W=mm <860/400=2.15mm 满足要求
说明:在1、2层梁上预埋Ф48*3.5钢管与支撑体系连接构成连墙杆件 。
8、Z49圆柱模板验算:
(截面为Φ1000mm,采用玻璃钢模安装,模高为6m,壁厚为8mm。)
8.1 平板玻璃钢圆柱模板的原理分析
根据流体力学的基本原理:圆环形容器壁在受到来自内部的液压力作用下要均匀胀大,故在包含圆环轴线的任何径向截面上,作用有相同的法向拉力。具有一定韧性的圆形容器,必定会撑胀成为一个标准的圆形柱体。这一理论的实现,在实际应用中,要满足以下两个条件:
(1)、玻璃钢模板是具有合适韧性的薄壁匀质体,受内部的液态压力能够胀成形圆。
(2)、混凝土在浇筑时呈流塑状,具有合适的流动度,在振捣的作用下,侧压力使不受约束的玻璃钢模板胀成圆形。
T/TMHIA 007-2022标准下载8.2 砼侧压力验算
F1=0.22r.t。.β1.β2.v1/2
=0.22×25×4.44×1.2×1.15×=57.76Kn/m2
F2=rc.H=25×3=75KN/m2
两者取最小值:P=F1=57.76K/m2
V为砼浇灌速度,β为商品砼影响系数,T为砼温度
t。=200/(30+15)=4.44
DB34/T 2630-2016 泵站计算机监控与视频监视系统检测规范8.3 平板玻璃钢圆柱模板的力学计算
(1)、取h=1000mm高度的模板截面,柱直径为1000mm,计算内力。